Construction Photos

BE SURE TO CLICK ON EACH BLOG TITLE TO SEE THE MOST RECENT PHOTOS OF THE CONSTRUCTION PROGRESS.


Saturday Road Closures

On Saturday, May 18, Main Street from Second Street to Gay Street will be closed for milling of the streets and utility installations. Cross street access at Gay Street, Tucker Street, 1st Street and 2nd Street will be open.


Sidewalk Demolition Began Today

Day 1 Construction on Downtown Erwin Revitalization Project


Sidewalk Demolition to Begin

Sidewalk demo will begin the morning of Wednesday, May, 15, starting at Gay Street and working north toward Tucker Street. The milling of the streets will begin on Saturday, May 18. Due to equipment logistics, Main Street from Gay to Second Streets will be closed during the milling of the surfaces. Main Street from Tucker[.....] View Full Post >>


The start of construction quickly approaching

Contractors are spending this week marking all underground utilities and finalizing surveying. Mobilization and construction are scheduled to begin Monday, May 13. The first step in the construction phase will be the milling of Main Avenue beginning at the Gay Street intersection and working toward the Second Street intersection.